Business Dystopia Post Automation Utopia v0.1 draft

DOC-06 PID

PID

Project Initiation Document for the transition programme

Programme
Post Automation Utopia programme
Document
PID
Version
v0.1 draft
Date
10 November 2026
Status
Draft for review. Not yet approved.
Owner
Programme Director
Approver
Programme Board

Purpose of this document

This Project Initiation Document (PID) defines the Post Automation Utopia programme: what it is for, what it will deliver, how it will be governed and controlled, and who is responsible for what. It gives the Programme Board the basis for authorising the programme and, at each phase gate, for deciding whether to continue.

The PID follows the PRINCE2 structure, tailored for a programme that runs for decades and is delivered by many institutions (see Tailoring of PRINCE2). It is a draft. Phase 0 will complete and baseline it.

Project definition

Background

Automation and AI are taking on a growing share of tasks. The IMF estimates that almost 40 per cent of global employment is exposed to AI, and about 60 per cent in advanced economies (IMF, 2024). The programme assumes that automation will in time be able to perform substantially all paid tasks, at a pace no one can predict.

Left unmanaged, that change would remove the wage as most people's source of income while the returns go to the owners of automated capital. The world starts from a weak position: 3.8 billion people have no social protection (ILO, 2024), about 3.4 billion lack adequate housing (UN-Habitat, 2026) and seven of the nine planetary boundaries have been crossed (Stockholm Resilience Centre, no date). The Draft plan sets out the evidence and lists its sources.

Objectives

By the time the programme closes, in every adopting country:

RefObjectiveIndicative measure
O1Every person has an unconditional income that is enough for an adequate standard of living.Share of residents at or above the adequacy benchmark.
O2Every person has an adequate, secure home and access to essential services.Number of people lacking adequate housing. Coverage of each essential service.
O3Automated systems are safe, accountable and under democratic control.Share of public-impact systems certified. Redress cases resolved. Participation in decisions about automation.
O4People have the learning, recognition and local institutions to live purposeful lives without depending on employment.Wellbeing and purpose indicators. Take-up of lifelong learning.
O5Nature is recovering, and the requirements of animals, plants and ecosystems are met.Planetary boundaries within safe limits. Red List Index. Area protected and restored.
O6The gains from automation are shared between countries.Gap in income floors and service coverage between groups of countries by income.
O7Entitlements are secured in law, and the arrangements hold a democratic mandate.Entitlements in national law. Number of states party to the compact.

Performance targets for the programme as a whole:

AspectTarget at v0.1
TimePhase 0 complete by June 2028. Later phases as in the Plan, with closure indicatively in 2057.
CostNot costed at v0.1. Effort is sized relatively in the Plan. The Phase 1 business case will set the first budget.
QualityDeliverables meet the quality criteria in this PID and the measures of success in the User Requirements Document.
ScopeThe seven pillars of the Draft plan. Every Must requirement in the User Requirements Document is met.
BenefitsThe eight benefits in the Business case, measured from baselines set in Phase 0.
RiskLow appetite for risks to safety, to ecosystems and to the incomes of vulnerable people. Moderate appetite for risks to the schedule.
SustainabilityNo programme activity adds to pressure on a planetary boundary that is already crossed, unless the Programme Board approves an exception with advice from the proxy panels.

Desired outcomes

People no longer depend on employment for a decent life, and are free to choose how to spend their time. Automated production is safe and its returns are widely shared. Living standards in low-income countries reach the same floors as elsewhere. Ecosystems and the species in them are recovering.

Scope and exclusions

In scope:

  • Economic security: an income floor, the automation dividend, tax reform and transition finance.
  • Homes for everyone and universal basic services.
  • Governance of automation and AI, including measurement, safety and accountability.
  • Purpose, learning and participation.
  • Planetary stewardship, including the representation of non-human users by proxies.
  • Fairness between countries.
  • Rights, law and legitimacy, including an international transition compact.
  • Programme governance, assurance, engagement and document control.

Out of scope:

  • Developing or operating automation technology. Industry does this, and the programme sets the conditions.
  • Prescribing how people live or what they consume (UR-054).
  • Preserving particular occupations as paid employment (UR-055).
  • Military uses of automation and AI, which belong to international security processes.
  • Decisions that belong to sovereign states. Countries choose whether and how to adopt the framework.

Constraints and assumptions

Constraints:

  • Adoption is voluntary. The programme cannot direct governments.
  • Human rights law and existing treaty commitments apply throughout.
  • Planetary boundaries limit how every pillar is delivered.
  • No sponsor or funding is confirmed (issue I-01).
  • Delivery relies on institutions with their own mandates and timetables.

The RAIDD records 10 assumptions. The ones the programme depends on most are:

  • Automation will in time be able to perform substantially all paid tasks, though the pace is uncertain (A-01).
  • Productivity gains from automation are large enough to fund adequate floors once a share is captured (A-02).
  • Enough states will join a coalition to make a compact viable (A-03).
  • Human proxies can represent non-human users credibly enough for decisions to rest on their advice (A-05).
  • Timelines and effort at v0.1 are indicative and relative. Nothing has been costed (A-09).

Tolerances

The Programme Director manages within these tolerances. A forecast breach goes to the Programme Board as an exception.

AspectTolerance
TimePhase 0: two months either side of the June 2028 end date. Later phases: twelve months either side of each phase end date.
CostNot set at v0.1. Until the Phase 1 business case sets it, any commitment beyond the resources agreed for Phase 0 needs Programme Board approval.
ScopeNo Must requirement is dropped or downgraded without Programme Board approval.
QualityNo departure from a safety, accessibility or welfare standard without Programme Board approval.
BenefitsAny forecast that a phase will miss a benefit target is reported to the Programme Board.
RiskAny risk scored 15 or more, and any new risk to life, rights or ecosystems, is reported to the Programme Board.
SustainabilityNo permitted deviation. Any activity that adds to pressure on a crossed planetary boundary needs an exception approved by the Programme Board.

Users and other interested parties

The User Requirements Document defines thirteen user groups and their requirements. In summary:

PartyInterestHow they are represented
All people, including children, older people, disabled people, carers, and workers and communities in transitionIncome, homes, services, purpose, safety and a say in decisions.Civil society and labour organisations, citizens' assemblies and the global consultation.
Indigenous peoplesRights to land, resources, culture and self-determination.Indigenous peoples' organisations, through free, prior and informed consent.
People in low-income countriesA fair share of the gains, and finance without unsustainable debt.National governments and Civil society and labour organisations.
Future generationsNo debt or ecological damage passed on to them.Youth organisations and an independent future generations function.
Wild animals, farmed animals, plants and fungi, ecosystems and the Earth systemHabitat, welfare, recovery and stable planetary conditions.Proxy panels hosted by Conservation science bodies and by Academia and research institutes.
Delivery institutionsClear mandates, standards and funding for what they are asked to deliver.Senior representatives on the Programme Board.

Interfaces

  • The Sustainable Development Goals and whatever follows them after 2030.
  • The Kunming-Montreal Global Biodiversity Framework and the Paris Agreement.
  • UN work on AI governance under the Pact for the Future and the Global Digital Compact.
  • ILO standards on social protection and just transition.
  • National social protection, housing, health and education systems.
  • Existing basic income, guaranteed income and Housing First programmes, whose evidence the programme will use.

Project approach

The programme will:

  • Work in phases, each authorised by the Programme Board at a gate.
  • Pilot before scaling, with independent evaluation of every pilot.
  • Set a common framework and leave delivery to national and local institutions.
  • Build on existing institutions and commitments in preference to creating new organisations. This is proposed and is to be confirmed (decision D-10).
  • Publish its evidence, data and decisions.
  • Move phase dates in response to the pace of automation measured by the observatory.
  • Treat the requirements of non-human users as constraints on design, with proxies to speak for them.

Business case

Reasons

If machines can do all paid work, wages stop being a workable way to distribute income, and the returns from production go to whoever owns the machines. No country has systems designed for that, and existing commitments on poverty, housing and nature are already behind. A planned transition can share the gains, protect people while work changes, and use the same period to restore the living world. An unplanned one leaves each of these to chance.

Options considered

OptionDescriptionAssessment
Do nothingLeave the adjustment to markets and existing welfare systems.Rejected. Most people would lose their income from work while returns concentrate among the owners of automated capital. Social protection reaches about half of the world's people today.
National action onlyEach country designs its own response.Not recommended on its own. Low-income countries could not fund floors, and capital could move to avoid dividend and tax measures.
Coordinated global programmeA common framework and compact, delivery by national and local institutions, and transfers between countries.Recommended. It deals with distribution within countries and between them, and gives non-human users a voice.
Slow or halt automationRestrict deployment in order to protect employment.Not recommended. It gives up the benefits and would be hard to enforce across borders. Controls on pace stay available where safety requires them.

Expected benefits

RefBenefitMeasureStarts to be realised
B1Income securityShare of people at or above the adequacy benchmark.Phase 1 in pilots, Phase 2 at scale
B2HomesNumber of people lacking adequate housing.Phase 1 in pilots, Phase 2 at scale
B3Essential servicesCoverage of health, food, water, energy, transport and digital services.Phase 2
B4Free time and wellbeingHours of paid work people need to do. Wellbeing indicators.Phase 3
B5Lower inequalityDistribution of income and wealth within and between countries.Phase 2 onwards
B6Safer automationCertified systems, incidents and redress outcomes.Phase 1 onwards
B7Recovery of naturePlanetary boundaries, Red List Index, and area protected and restored.Phase 2 onwards
B8LegitimacyPublic trust and participation. States party to the compact.Phase 0 onwards

Expected dis-benefits

  • Disruption to pension and benefit systems while they are migrated.
  • Lower returns or higher taxes for owners of automated capital.
  • Loss of the status and identity that people draw from their occupations.
  • New administrative work for governments, especially where delivery systems are weak.
  • Pressure on land from new housing.

Timescale

Five phases from January 2027, with closure indicatively in 2057. See Project plan.

Costs

The programme is not costed at v0.1. The Plan sizes effort relatively as Small, Medium, Large or Very large. Phase 0 needs a small programme team, commissioned research and a worldwide consultation. The cost of Phases 1 to 4 falls mostly on delivery institutions. It will be estimated in the financing strategy (P0-10) and the Phase 1 business case.

Investment appraisal

Deferred until Phase 0 has quantified the costs and benefits.

Major risks

The RAIDD holds 16 risks. The highest rated are: political mandate is not won or is lost; automation moves at a different pace from the scenarios; ownership of automated capital concentrates; inequality between countries widens; automation pushes ecological limits further; automated systems are unsafe or unaccountable.

Project management team structure

The table maps PRINCE2 roles to the programme's roles. The same role names are used in the Plan, the RAIDD and the RACI.

PRINCE2 roleProgramme roleNotes
ExecutiveSponsorChairs the Programme Board.
Senior UserProgramme Board members from Civil society and labour organisations, Indigenous peoples' organisations and the proxy panelsSpeak for the people and the non-human users who will live with the results.
Senior SupplierProgramme Board members from National governments, Regional and local governments, UN bodies, Central banks, International financial institutions and IndustrySpeak for the institutions that deliver.
Project ManagerProgramme DirectorRuns the programme day to day.
Project SupportPMO LeadPlanning support, reporting, the RAIDD log and the Control register.
Change AuthorityDesign Authority LeadDecides changes to requirements and design within tolerance.
Project AssuranceBenefits and Assurance LeadReports to the Programme Board independently of the Programme Director on assurance matters.
Team ManagersThe seven workstream leadsEach leads one workstream and coordinates the delivery institutions in it.

Role descriptions

The RACI shows responsibilities action by action. The roles are:

RoleTypeMain responsibilities
SponsorProgramme governanceSenior responsible owner, nominated by the sponsoring institutions. Owns the case for the programme, chairs the Programme Board and is answerable for its outcomes.
Programme BoardProgramme governanceSenior decision-making body: the Sponsor, the Programme Director and senior representatives of users and of the delivery institution types. Approves phases, tolerances and exceptions.
Programme DirectorProgramme governanceLeads the programme day to day within the tolerances set by the Programme Board. Owns the integrated plan and the management of risks and issues.
PMO LeadProgramme governanceRuns the Programme Management Office: planning support, reporting, the RAIDD log, document control and the Control register.
Design Authority LeadProgramme governanceOwns the requirements baseline, the end-to-end solution design and traceability. Acts as change authority and arbitrates design trade-offs between workstreams.
Benefits and Assurance LeadProgramme governanceOwns benefits realisation, quality, independent assurance and phase-gate reviews.
Economic Security LeadWorkstream leadLeads the workstream on the income floor (universal basic income), the automation dividend, public wealth funds, fiscal design and transition finance.
Basic Services LeadWorkstream leadLeads the workstream on homes for everyone and universal basic services: health, food, water, energy, transport and digital access.
Automation and AI Governance LeadWorkstream leadLeads the workstream on measuring automation and on the safety, standards and accountability of automated systems.
Purpose, Learning and Participation LeadWorkstream leadLeads the workstream on lifelong learning, support for displaced workers, recognised contribution and participation.
Planetary Stewardship LeadWorkstream leadLeads the workstream on ecological limits, biodiversity, animal welfare and the proxy panels for non-human users.
Engagement and Legitimacy LeadWorkstream leadLeads stakeholder engagement, global consultation, communications and the democratic mandate.
Legal and Policy LeadWorkstream leadLeads the workstream on rights, law, the international compact and policy alignment.
National governmentsDelivery institutionLegislate, fund and deliver national income floors, services and regulation.
Regional and local governmentsDelivery institutionDeliver housing, local services, land-use planning and local participation.
UN bodiesDelivery institutionConvene states, host the transition compact, and set and monitor global standards.
Central banksDelivery institutionAdvise on monetary and financial stability, run payment infrastructure and steward public wealth funds where mandated.
International financial institutionsDelivery institutionProvide development finance, global transfers and fiscal analysis for low- and middle-income countries.
IndustryDelivery institutionBuilds and operates automated production, construction and services, and contributes to the automation dividend.
Civil society and labour organisationsDelivery institutionRepresent citizens, workers and specific groups of people, run community services and hold the programme to account.
Indigenous peoples' organisationsDelivery institutionRepresent Indigenous peoples, give or withhold free, prior and informed consent, and contribute traditional ecological knowledge.
Conservation science bodiesDelivery institutionAct as proxies for wild animals, plants, fungi and ecosystems, and monitor biodiversity and ecosystem condition.
Academia and research institutesDelivery institutionProvide evidence, modelling and independent evaluation, and act as proxies for farmed animals and the Earth system.

Quality management approach

The Benefits and Assurance Lead is accountable for quality. Every deliverable is checked against these criteria before the Programme Board accepts it:

  • It rests on cited evidence.
  • It traces to requirements: from the User Requirements Document, through the Solution Requirements Document, to the Plan.
  • Its effects on equality and on future generations have been assessed.
  • Its ecological effects have been assessed with advice from the relevant proxy panel.
  • It is written in plain language and is available in accessible formats.
  • The roles shown as consulted in the RACI have reviewed it.

Quality is checked by peer review, by independent evaluation of pilots, by proxy panel review and by independent assurance at each phase gate. The PMO Lead keeps the quality records, and the Control register lists the approved version of every document.

Change control approach

  • Baselines. Documents are drafts while their version starts with 0. A version starting with 1 or higher is a baseline approved by the role named as approver in the Control register.
  • Raising a change. Anyone may raise an issue or a request for change. The PMO Lead logs it in the RAIDD.
  • Assessing it. The Design Authority Lead assesses the effect on requirements, plan, benefits and risks.
  • Deciding. The Programme Director decides changes within tolerance. The Design Authority Lead decides changes to requirements and design within tolerance. Anything beyond tolerance goes to the Programme Board.
  • Recording. The PMO Lead updates the affected documents and the Control register. Requirement IDs are never reused.

Risk management approach

Any role may identify a risk. Each risk is scored for likelihood and impact from 1 to 5, and the two are multiplied. A score of 15 or more is Red, 8 to 14 is Amber, and lower scores are Green. Each risk has one owner and a response: avoid, reduce, transfer, share, accept or prepare a contingency.

  • The Programme Director is accountable for risk management, and the PMO Lead maintains the RAIDD.
  • The RAIDD is reviewed monthly in Phase 0, quarterly afterwards, and at every phase gate.
  • The Programme Board reviews every Red risk.
  • Data from the automation observatory is used as an early warning. If measured displacement runs ahead of the scenarios, the Programme Board reviews the timing of the phases.

Communication management approach

Communication is open by default, runs in both directions, and uses people's own languages and accessible formats.

AudienceWhat they needHow and how oftenOwner
Programme BoardProgress, exceptions and decisions needed.Highlight reports monthly in Phase 0 and quarterly afterwards. Exception reports when needed.Programme Director
Delivery institutionsPlans, standards and pilot results.Workstream groups, and a forum each quarter.Workstream leads
The publicPlain-language updates, open data and a way to respond.Publication, consultation and citizens' assemblies, continuously.Engagement and Legitimacy Lead
Indigenous peoplesEarly information on anything affecting their lands, resources or cultures.Through Indigenous peoples' organisations, under the consent protocol.Engagement and Legitimacy Lead
Proxy panelsImpact assessments and monitoring data.Twice a year, and whenever a decision has an ecological impact.Planetary Stewardship Lead
Workers and affected communitiesEarly notice of sector automation assessments.Through labour organisations and local government, as assessments are made.Purpose, Learning and Participation Lead

Benefits management approach

The Benefits and Assurance Lead owns the benefits map. Phase 0 will write a profile for each of the eight benefits, with a baseline, a measure, an owner and a target for each phase. Benefits are reviewed at every phase gate. Most are realised after the pilots, and many continue after closure, so the permanent stewardship institutions take over the tracking in Phase 4.

Sustainability approach

The requirements of non-human users in the User Requirements Document are treated as constraints on how every pillar is delivered. The programme sets a planetary footprint budget for automation infrastructure, takes advice from the proxy panels before any decision with an ecological impact, and applies the sustainability tolerance above. The Planetary Stewardship Lead reports against the budget at every phase gate.

Project plan

The Plan lists every step with timing, effort, owner and dependencies. The phases are:

PhaseNameIndicative datesAim
Phase 0Finalise the planJanuary 2027 to June 2028Take the v0.1 draft to an approved final plan with a mandate for Phase 1.
Phase 1Foundations and pilotsJuly 2028 to December 2032Set up the institutions, measurement and safety regime, and pilot every pillar at scale in a range of countries.
Phase 2Scale national floorsJanuary 2033 to December 2040Legislate and scale income floors, basic services and housing, fund them from the automation dividend, and restore nature at scale.
Phase 3Transition at scaleJanuary 2041 to December 2055Raise floors to sufficiency as automation approaches full coverage, separate livelihood from employment, and bring living standards together across countries.
Phase 4StewardshipFrom January 2056Hand over to permanent stewardship institutions and close the programme.

Key milestones, with indicative dates:

MilestoneIndicative datePlan step
Programme mobilised and PID approvedMarch 2027P0-01
Evidence review completeOctober 2027P0-04
Global consultation completeMarch 2028P0-07
Requirements baselinedApril 2028P0-08
Final plan approved and Phase 1 authorisedJune 2028P0-13
Automation observatory publishingDecember 2029P1-02
Transition compact open for signatureDecember 2030P1-01
Phase 1 evaluated and scale-up decidedDecember 2032P1-12
Income floors in law in adopting countriesDecember 2037P2-01
Mid-programme review completeDecember 2040P2-10
Income floors raised to sufficiencyDecember 2055P3-01
Human activity back within planetary boundariesDecember 2055P3-05
Programme closed and handed overDecember 2057P4-02

Project controls

  • Phase gates. The Programme Board authorises each phase after an end-phase report and an independent assurance review.
  • Highlight reports. From the Programme Director to the Programme Board, monthly in Phase 0 and quarterly afterwards.
  • Checkpoint reports. From each workstream lead to the Programme Director, monthly.
  • Exception reports. Raised by the Programme Director as soon as a tolerance is forecast to be exceeded.
  • Logs and registers. The RAIDD for risks, assumptions, issues, decisions and dependencies. The Control register for documents. A quality register and a lessons log kept by the PMO Lead.
  • Reviews. Independent assurance at each gate, and a mid-programme review in 2040.

Tailoring of PRINCE2

  • The project is a programme of many projects. Its phases act as management stages, and each workstream project inside a phase would have its own lighter PID.
  • Phase 0 combines initiation with the first delivery stage, because finishing the plan is the first deliverable.
  • The user side of the Programme Board includes proxies for non-human users and a voice for future generations.
  • The business case uses relative sizing until Phase 1.
  • A single RAIDD replaces the separate risk register, issue register and daily log, and adds decisions and dependencies.
  • Sustainability is a seventh performance target, as in the seventh edition of PRINCE2.
  • Sovereign institutions deliver most of the later phases. The programme sets standards and coordinates, so accountability for those steps sits with types of institution in the RACI.

The programme documents are listed below. The Control register holds the current version and link for each.

DocumentWhat it holds
Draft planOutline of the transition plan and the evidence behind it.
Next stepsRecommended steps to take the draft plan to a final version (Phase 0).
PlanThe programme's steps, with timelines, effort, owners and dependencies.
RAIDDRisks, assumptions, issues, decisions and dependencies, with owners.
RACIWho is responsible, accountable, consulted and informed, at high level and in detail.
User Requirements DocumentRequirements of people, animals, plants, ecosystems and the Earth system, each with a MoSCoW priority.
Solution Requirements DocumentWhat the programme must put in place, with each requirement traced to the User Requirements Document.
ControlThe document register: every programme document with its version, owner and link.